Web Applications Stack Exchange is a question and answer site for power users of web applications. It's 100% free, no registration required.

Sign up
Here's how it works:
  1. Anybody can ask a question
  2. Anybody can answer
  3. The best answers are voted up and rise to the top

Jira → Agile → Scrum Board → Work has columns with these titles:

  • To Do
  • In Progress
  • Done

Can the text for these titles be changed?

share|improve this question
up vote 2 down vote accepted

In version 6 of Greenhopper (Agile) and probably earlier versions, you can do this by going to the Scrum Board, then selecting Tools > Configure from the menu on the right. Then select the Columns tab if it isn't already and you should then be able to in-line edit the titles by clicking on them.

share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.