2

In Jira, I have subtasks with estimates.

Task X (0 hours)

  • Subtask A (4 hours)
  • Subtask B (8 hours)
  • Subtask C (10 hours)

When I view the parent task, the estimated time does not display the sum of the subtask estimates.

Is there any way to get these to auto populate?

Your Answer